Now they’ve done it.

They’ve failed to finish new facilities for Borey-class SSBNs on Kamchatka expeditiously, and they’ve forced Defense Minister Sergey Shoygu to demand “strict control” over their work.

But who “they” are isn’t exactly clear.

According to Mil.ru and RIA Novosti, the annoyed Shoygu said:

“These things are too serious to joke about the time period for their construction.  The joking is over.”

As regards the current plan to base Borey units 2 and 3 at Rybachiy (presumably in 2015):

“At that time everything must be ready.”

Mil.ru reported that the Defense Minister was also dissatisfied with the quality of the construction he observed.

Shoygu laid responsibility on General Staff Chief, Army General Valeriy Gerasimov and Eastern MD Commander, General-Colonel Sergey Surovikin, ordering them to take the work at Rybachiy under “strict control” and to give him a weekly progress report.

Shoygu should have turned to his old friend and subordinate from MChS days, Aleksandr Volosov, who directs the Federal Agency for Special Construction (Spetsstroy).  Spetsstroy is building the new pier zone at Rybachiy.  It used to be known as the Main Directorate for Special Construction (GUSS) in the old days when it fell squarely under the MOD.

Rybachiy and Environs

Rybachiy and Environs

The current Defense Minister’s not the first to ask when his sub base will be ready.

In 2012, President Vladimir Putin revealed that he arranged significant financial assistance from two Russian oil companies to keep the Pacific Fleet strategic sub base open in 2002.

He visited periodically to check progress in modernizing its naval and social facilities.  He was usually unhappy with what he found.

Speaking from Vilyuchinsk in 2004, Putin said:

“They told me here in the past two years an improvement [in military living conditions] was being felt, but I didn’t see this.  The material base of public facilities here is in a pathetic state.  This situation is absolutely intolerable.”

By 2007, according to Izvestiya, he saw some improvement, but still said officials were “just picking their noses” instead of getting Gazprom to gasify Kamchatka.  Army General Anatoliy Grebenyuk, chief of the MOD’s billeting and construction service, and the chief of the Main Military-Medical Directorate were unceremoniously retired for failing to finish their respective work on the remote peninsula.

Gazprom reports that Petropavlovsk-Kamchatskiy was gasified in 2010, but it’s unknown if local gas lines have, as yet, reached the sub base.

As it has long planned, Moscow intends to homeport four Borey-class SSBNs on Kamchatka, starting with Aleksandr Nevskiy and Vladimir Monomakh.  But first it wants a fully functioning system in place to support their operations.

In March, a Navy Main Staff source told ITAR-TASS that the complete system for basing the new submarines – piers, utilities, logistical support, weapons storage facilities, and other infrastructure – still needs to be finished. Consequently, neither SSBN will arrive in the Pacific Fleet earlier than the fall of 2015.

Popovkin Details the GPV

Yesterday First Deputy Defense Minister Vladimir Popovkin gave RIA Novosti more details on Russia’s procurement plans under the State Program of Armaments (GPV), 2011-2020.  He said 78-80 percent of the 19-trillion-ruble Armed Forces portion of the GPV will go to procurement.   

Popovkin said Russia plans to develop a new liquid-fueled heavy ICBM to carry up to ten warheads, and having a service life of up to 35 years.  Former RVSN Commander General-Lieutenant Andrey Shvaychenko talked about a new liquid heavy as far back as late 2009, and the issue’s been debated in the Russian military press since. 

Popovkin said the Defense Ministry plans to accept the Bulava SLBM and the first two Borey-class SSBNs this year.  There will be 4-5 Bulava launches this year.  Recall to date only 7 of 14 Bulava tests have been successful.  Addressing the missile’s past failures, Popovkin said there were many deviations from the design documentation during production.  He also said Russia plans to build eight SSBNs to carry Bulava by 2020.  He was unclear if this includes the first two Borey-class boats.

Popovkin said work on a new strategic bomber is ongoing, and he claimed a technical design will be complete in 2015.  He said this work isn’t being rushed.

Popovkin told RIA Novosti  the Air Forces will receive more than 600 new aircraft and 1,000 new helicopters by 2020.  In 2011, Su-27SM, Su-30M2, Su-35S, Yak-130, and Su-34 aircraft are to be procured.  More than 100 helicopters, including Mi-26 transports and Mi-28N and Ka-52 combat helicopters will be acquired this year, according to Popovkin. 

Popovkin said a contract for the first ten experimental PAK FA (T-50) aircraft will be signed in 2013, with serial production of 60 aircraft beginning in 2016.

The GPV includes the purchase of ten S-500 air defense systems.  Popovkin said this system will begin testing in 2015, initially with missiles from the S-400.  Fifty-six S-400 units will also be purchased by 2020.  This sounds like seven 8-launcher battalions.   

Popovkin said the GPV will buy 100 ships – including 20 submarines, 35 corvettes, and 15 frigates – for the Navy.  He didn’t specify types for the other 30 ships, and it’s unclear if new SSBNs are included in these numbers.  Popovkin reconfirmed Russia’s plan to buy two and build two Mistral amphibious ships.  Recall also the Black Sea Fleet alone is supposed to get 18 new ships including proyekt 636 diesel-electric submarines, proyekt 11356 and 22350 frigates, and proyekt 11711 LSTs.

Popovkin also mentioned plans to buy a limited number of French FELIN soldier systems, with the intent of Russia producing its own version by 2020.  He looks for it to equal the advertised capabilities of U.S. and German equivalents.

Aleksandr Nevskiy Launch Planned

According to ITAR-TASS, Sevmash shipbuilders have announced they’ll launch the second proyekt 955 Borey-class SSBN Aleksandr Nevskiy at the end of November.  Nevskiy was laid down on 19 March 2004.  Lead unit Yuriy Dolgorukiy is preparing for a test launch of the Bulava SLBM likely in December.

ITAR-TASS says Borey unit 3 Vladimir Monomakh (laid down in 2006) is on a buildingway at Sevmash.  Nevskiy and Monomakh were not identified as proyekt 955A boats.  The wire service also didn’t mention anything about an official lay down for hull 4 (Sv. Nikolay).  Plans are for not less than 8 of the Borey SSBNs.