Tag Archives: SSBN

Solomonov and Bulava

Bulava designer Yuriy Solomonov seems to have come out from underground now that the Bulava SLBM has some successes under its belt.

Yesterday the Russian media carried excerpts from a soon-to-be-published interview with Igor Korotchenko’s Natsionalnaya oborona

Solomonov already has a book about his adventures in missile design to his credit.  The only thing that’s changed is the Bulava program seems to be righting itself.

Solomonov said, not surprisingly, that the Bulava’s warheads are ready, and he expects the missile to stay in the inventory until 2050.

He expects Votkinsk to ramp up for Bulava production.  He noted that, for a facility that produced 100 missiles a year in Soviet times, “Now there isn’t any kind of problem from the point of view of organizing the technological process and organizing people for this task.”

Solomonov said Borey-class SSBN Yuriy Dolgorukiy will begin (like Dmitriy Donskoy did) with a surface test launch.  But he doesn’t rule out that this could be changed to a submerged launch.  The tentative date is 17 December. 

He forecasts 4 tests in 2011, the start of serial Bulava production, and possibly the missile’s acceptance into the Navy arsenal, if it achieves a “high reliability coefficient.”

In the interview, Solomonov apparently will talk about how Bulava could be adapted into a ground-launched missile.  This brings back the whole issue of “inter-service unification,” which led to some of the excitement with Bulava.

Svpressa.ru and Anatoliy Tsyganok have a good time lambasting Solomonov for this (again) if you want to take a look.

Dolgorukiy, Bulava, Severodvinsk

Submarine-related news notes . . .

Russian press services have announced that the state commission on the Bulava has finished analyzing the results of the last two launches.  The next test will be in the second half of December, and the exact date will depend on White Sea weather conditions.

It’s pretty, but not absolutely, certain that new Borey-class SSBN Yuriy Dolgorukiy will be the launch platform.  The final decision on this will be made in the first ten days of December.  One supposes another shot from Dmitriy Donskoy remains a remote possibility.

If the pending launch is a success, the next phase of testing will begin in May 2011.

Regarding fourth generation (proyekt 885, Yasen) SSN Severodvinsk, the boat is still fitting out, and the Navy expects it to join the fleet in 2011.  Like DolgorukiySeverodvinsk was under construction for many years.  ITAR-TASS said this morning 6 of these submarines are now planned.

Aleksandr Nevskiy Launch Planned

According to ITAR-TASS, Sevmash shipbuilders have announced they’ll launch the second proyekt 955 Borey-class SSBN Aleksandr Nevskiy at the end of November.  Nevskiy was laid down on 19 March 2004.  Lead unit Yuriy Dolgorukiy is preparing for a test launch of the Bulava SLBM likely in December.

ITAR-TASS says Borey unit 3 Vladimir Monomakh (laid down in 2006) is on a buildingway at Sevmash.  Nevskiy and Monomakh were not identified as proyekt 955A boats.  The wire service also didn’t mention anything about an official lay down for hull 4 (Sv. Nikolay).  Plans are for not less than 8 of the Borey SSBNs.

Another Bulava Success

Bulava Launch (photo: ITAR-TASS)

At 0510 MSK today, Dmitriy Donskoy successfully launched the second Bulava SLBM of 2010 while submerged in the White Sea.  That makes two in a row, and 7 successes in 14 attempts overall. 

A government Military-Industrial Commission (VPK) source told ITAR-TASS the 15th test could occur in early December and will be the first from new Borey-class SSBN Yuriy Dolgorukiy.  The source attributed the successes to a tightening of control over the production and state acceptance processes.  He also warned it’s too early to relax:

“Two successful launches don’t signify that it’s possible to accept ‘Bulava’ into the arsenal.  A great deal will depend on testing in 2011.”

A member of the state commission that investigated the Bulava failures told RIA Novosti that these successes show Bulava had assembly problems.  And he said testing will continue in 2011.

RIA Novosti noted that, perhaps most significantly, this year’s Bulava tests came from a submerged boat.  In 12 tests prior to 2010, there had not been a single successful underwater launch.

Strategic Forces Training

Russia fired two SLBMs and an ICBM today.  Pacific Fleet Delta III SSBN Saint Georgiy Pobedonosets launched an SS-N-18 (RSM-50) SLBM from the Sea of Okhotsk.  Northern Fleet Delta IV SSBN Bryansk fired a Sineva (RSM-54) SLBM from the Barents Sea. 

And a crew from the Vladimir Missile Army’s Bologoye Division launched an SS-25 (RS-12M/Topol) ICBM from Plesetsk.

An RVSN spokesman said this launch allows Russia to extend the service life of this grouping of SS-25s to 23 years or until about 2015, and to conduct a planned replacement of these missiles without overburdening the military’s budget.

Yesterday Tu-95MS and Tu-22M3 bombers launched weapons on ranges in Irkutsk and Komi as part of an Air Forces exercise.

According to some reports, the Navy may test fire the Bulava SLBM for the second time in 2010 tomorrow.

Dizzy with Bulava’s Success?

Iosif Vissarionovich might have accused Bulava’s proponents of dizziness after the SLBM’s test firing on October 7.  There’s no mistaking it was a clear boost to a troubled program.  Success always trumps failure.  It may even turn out that all of Bulava’s design, production, and assembly problems are resolved.  But one would think the history and current state of the Bulava would call for more cautious, guarded optimism.  This successful test was necessary, but far from even close to sufficient to complete the program.

The biggest news story after this successful test was the report that, as a result, the Bulava SLBM and Borey-class SSBN weapons system might be accepted into the arms inventory as early as mid-2011.

A highly-placed Navy Main Staff source told Interfaks:

“Before the end of the year, another two test launches of the missile are planned, if they are as successful as today’s launch, then it’s legitimate to consider the issue of the quickest completion of tests of this strategic system.  I’m proposing that the acceptance of Bulava into the arms inventory could happen in the middle of next year.”

He follows adding that serial production of the SLBM and its deployment in proyekt 955 Borey-class SSBNs will ensue.

The Navy Main Staff source doesn’t go into exactly what ‘quickest completion’ entails, but others do.  Presumably, this means another test from Dmitriy Donskoy before the end of October and, if that’s a success, the first launch from Borey-class Yuriy Dolgorukiy before year’s end.

Vesti.ru conjectures that ‘quickest completion’ might mean a second, ‘insurance’ shot from Yuriy Dolgorukiy in early 2011, then a volley firing of two missiles in spring or early summer.  After this, if every test is a success, the weapons system would be accepted, serial production would begin, and Bulava would be deployed on Yuriy Dolgorukiy.  That’s if everything goes right.

An irrationally exuberant Defense Ministry source even told RIA Novosti:

“The successful launch of the missile gives a basis to suppose that the entire system ‘submarine plus missile’ will be accepted into the Russian Navy’s arms inventory by the end of the year or at the beginning of next.”

Former Armaments Chief Anatoliy Sitnov was pretty confident, telling Interfaks and ARMS-TASS that no specialists are expressing doubts about Bulava, and ‘broken links’ in its production process have been overcome.

Old RVSN general Viktor Yesin told Interfaks he agrees it’s possible to plan for completing Bulava testing by mid-2011.  But he retains some caution:

“The tests conducted instill hope that the two flight tests of the Bulava ballistic missile coming before the end of this year will be successful.  If this happens, it’ll be possible to confirm that the designers and producers overcame a period of failures in the creation of the new submarine-launched missile system.”

Yesin also notes that only the telemetry can say if all the Bulava’s systems were working normally.

Forum.msk’s Anatoliy Baranov is skeptical about making Bulava part of Russia’s strategic nuclear forces even if the next two tests are successful, and make the tally 8 successes in 15 attempts.  He says having a missile you want to produce doesn’t mean you can produce it quickly in the necessary quantity:

“Incidentally, no one has answered for the strategic decision which left the country practically without a naval component of strategic nuclear forces [SYaS].  Don’t believe that the resignation of MIT director Solomonov is a sufficient measure of responsibility considering the possible consequences of such a mistake, and the fact that today our naval strategic nuclear forces [MSYaS] already lag the strategic enemy by a factor of 5.  But even given the most successful confluence of circumstances, we will have a gap between old missiles and submarines going out of service and new ones coming into service because the possibilities of domestic industry in serial production of solid-fuel missiles are very limited.  The Votkinsk factory produces 5-6 solid-fuel ‘Topol-M1’ missiles, there aren’t other producers.  This means the production of new missiles of the ‘Bulava’ type puts an extra load on production which already can’t cope with the creation of new land-based missiles — see, straining the RVSN rearmament program even worse.  In the best case, the necessary complement of armaments for the 3 new ‘Borey’ class SSBNs will be produced in nearly 15 years.  This is a catastrophe.”

Andrey Ionin doesn’t agree with Sitnov above.  He told Gazeta.ru that the Defense Ministry shouldn’t be impatient:

“A state commission report on successful testing and a formal decision on accepting the system for regular use doesn’t change the fact that the problem of low quality in joint production has not been eliminated.”

Carnegie Center Moscow associate Petr Topychkanov says:

“Three successful tests in a row is not a reason to put a type into serial production.”

But, unlike Baranov, he points out that the production run for Bulava doesn’t have to be too big since there are, and will be, relatively few tubes to fill.

Pavel Felgengauer in Novaya gazeta is skeptical about how close the Bulava RVs came to their intended targets, but, more important for this discussion, he calls saying that Bulava is almost ready for deployment after this successful test a “dangerous adventure.”  He adds:

“And here is a ‘raw’ missile, not completely ready and the not tested ‘Yuriy Dolgorukiy,’ a crew which clearly hasn’t mastered its submarine — and missile launches right away.  Very bold to put it mildly.”

Viktor Baranets sums it up:

“A successful launch instills some optimism.  But it’s still a long time before accepting the missile into the arms inventory.  And of 13 launches only 6 (including yesterday’s) [October 7]  were recognized as successful.  Or ‘partially successful.’  But this is not cause to launch the missile into a serial run.  Higher ‘positive indicators’ are needed.  Our specialists and foreign ones believe the quantity of successful launches should be steadily above 90%.”

Litovkin on What the GPV Will Buy

Viktor Litovkin (photo: RIA Novosti)

Returning to procurement and the GPV . . . in this week’s Delovoy vtornik, NVO’s Viktor Litovkin also asks what will 19 trillion rubles be spent on. 

He says the answer isn’t simple.  During the last 20 years of ‘starvation rations,’ the armed forces got handfuls of essential combat equipment, and, meanwhile, a dangerous imbalance between strike and combat support systems was created.  And this was obvious against Georgia in 2008. 

Litovkin says this imbalance has to be corrected, meanwhile priorities like strategic nuclear forces can’t be forgotten – not just the offensive triad, but also the missile attack early warning system (SPRN), missile defense (PRO), and aerospace defense (VKO). 

Like Viktor Yesin of late, Litovkin asks how Russia will replace its aging strategic offensive arms to stay up to the limits of the Prague / New START agreement.  Half the Russian force is SS-18, SS-19, and SS-25 ICBMs which will be retired in 7-10 years.  Moscow needs to build 400 strategic systems to replace them.  He doesn’t even mention Delta III and IV SSBNs and their aging SLBMS.  And Russia has only the SS-27, RS-24 Yars, Sineva, and Bulava to replace them. 

Litovkin expects a very large amount of money to be spent not just on replacing strategic systems, but also reequipping the enterprises that produce them. 

He turns to his second priority – also demonstrated by the Georgian war – precision-guided weapons, which in turn depend on reconnaissance-information support and equipment in space, on long-range surveillance aircraft [AWACS], and UAVs. 

Priority three – automated command and control systems (ASU).  He cites Popovkin on linking all service C2 systems into one system over 2-3 years. 

Litovkin says you can’t forget about the Navy, but he mentions just the Borey-class SSBNs, and the need for a wide range of surface ships.  And he makes the point [made by many] that Mistral is all well and good, but it’ll have to have multipurpose combatants operating in its battle group.  They need to be built, and they won’t cost a small amount of money. 

One can’t forget aviation either.  Litovkin cites a $100 million per copy cost for 60 fifth generation fighters [that’s a significant 180-billion-ruble bite out of the GPV].  He notes Vega is working on an updated Russian AWACS (A-100).  And, like Korotchenko, he mentions transport aircraft, but also combat and support helicopters. 

And so, says Litovkin, the question arises – isn’t the country putting out a lot of money to rearm its army? 

Viktor Litovkin (photo: Ekho Moskvy)

Being bold, he says, not really.  He actually uses that accursed 22 trillion figure, which is procurement for all power ministries.  If he used 19 trillion, it would be 1.9 trillion or $63 billion per year for Russia against $636 billion for the U.S., $78 billion for China, $58 billion for the U.K., and $51 billion for Japan.  But he doesn’t say this is annual procurement, the GPV, against the total annual defense budget for these other countries.  A bit of comparing one piece of pie to a whole pie.  Nevertheless, he concludes this makes Russia far from champion when it comes to military expenditures. 

Litovkin’s last word is Russia will remain one of the G8 with a powerful, combat capable, and effective army, but without it, only a raw materials appendage of either the West or East. 

But one wonders, hasn’t Russia long been in the G8 without that kind of armed forces?  Doesn’t breaking away from the raw materials supplier role have more to do with developing an open, attractive, innovative, value-added, and competitive economy (and a political system and society to match) than with military power? 

Dolgorukiy Factory Testing Complete

Borey-class SSBN Yuriy Dolgorukiy

Not a huge news story, but worth keeping continuity on . . . and there are interesting questions — has the fourth Borey really been laid down, and how many launch tubes will be on unit 2, 3, etc.? 

Borey-class SSBN Yuriy Dolgorukiy completed its factory underway testing by 24 September, according to the official Russian news services.  A spokeswoman for Sevmash said the current testing plan was fulfilled, and all established tasks were completed.  Captain First Rank Vladimir Shirin called the last at-sea period ‘excellent.’  All systems reportedly worked well, and minor issues noted during previous cruises were resolved.  The Sevmash delivery team and Dolgorukiy crew are preparing to present the submarine to the state acceptance commission.  But according to Grani.ru, a United Shipbuilding Corporation (OSK) source told Interfaks the obvious – acceptance of Dolgorukiy into the Navy inventory is not being considered since its main weapon – the Bulava SLBM – is not ready.  The Defense Ministry is still hoping that the new SSBN will be the launch platform for one of the next three Bulava tests.

The news services noted there are two additional Boreys, not three, on Sevmash’s buildingways.  So one supposes number four, Saint Nikolay, hasn’t been laid down yet.

The news services maintain the line that the Borey-class boats will have 12 launch tubes each, but Grani.ru, like other media outlets, claims Aleksandr Nevskiy and Vladimir Monomakh are proyekt 955A units and will have 16 tubes, while Saint Nikolay will be a proyekt 955U boat, possibly with 20 tubes.

Possible Bulava Test By Mid-September

Bulava (photo: Newsru.com)

An OPK source has told ITAR-TASS the next Bulava SLBM test is expected in the first half of September.  The source said the state commission investigating the last Bulava failure is scheduled to meet 6 September, and the launch window for the next test opens on 9 September.

A missile industry source told Interfaks the commission will meet in the 5-7 September timeframe, and it could fix a launch date sometime at the end of the first ten days of September.

Newsru.com recalled that three tests are planned for 2010:  two from Dmitriy Donskoy and one from Borey-class SSBN Yuriy Dolgorukiy.  The website’s Defense Ministry source unofficially repeated claims that, if all three firings are successful, the Bulava will be accepted into the armaments inventory next year.

ITAR-TASS also reported today that Dolgorukiy successfully completed its latest phase of factory underway trials, and is preparing to go sea again next month.  Sevmash reports the new SSBN completed its cruise program, showing “good performance characteristics and reliable working of all onboard systems.”

Defective Bulava Nozzle

That same highly-placed RIA Novosti source in the Navy Main Staff also said the next Bulava SLBM test will occur in August or September from Dmitriy Donskoy.  A favorable outcome would led to another test launch from Dmitriy Donskoy, then a third launch from the missile’s intended platform Yuriy Dolgorukiy.

RIA Novosti also reported a source — close to the state commission investigating the cause of the last failed Bulava launch — said yesterday that the cause of the unsuccessful December 2009 test was a malfunctioning rocket nozzle.  He said:

“The state commission established that the nondeployment of Bulava’s extendible nozzle between the missile’s first and second stages was the cause of the last unsuccessful launch.”

He added that the nozzle problem was not caused by a design flaw, but by a production defect, and the missile was simply made incorrectly.

RIA Novosti recalled that First Deputy Defense Minister Popovkin, on 30 June, said only that the commission had recommended continuing Bulava testing.  He didn’t comment on any conclusions on the cause of the last Bulava failure.