Tag Archives: Severodvinsk

Tsar-Boat

Russian military television, TV Zvezda, not long ago ran a 35-minute show on the construction and acceptance of Borey-class SSBN Vladimir Monomakh in Severodvinsk.  Pretty interesting footage showing test launches of Bulava SLBMs and engineers checking design specs on reams of paper documents.  Props to someone for putting the video on YouTube.

The program follows MOD military representatives, civilians, and crew through the final process of delivering and accepting the new submarine into service.  It also has footage from Votkinsk showing the manufacture of Bulavas for the Borey-class.

Ambitious Sub Building Plans

This news is dated, but wasn’t picked up widely (if at all).

Sevmash is a Busy Place, Likely to Get Busier

Sevmash is a Busy Place, Likely to Get Busier

Russia will start construction on eight nuclear-powered submarines in 2014-2015, according to the chief of Sevmash.

In 2015, Russia will lay the first sections of two Borey-class nuclear-powered ballistic missile submarines (SSBNs) and three Yasen-class attack submarines (SSNs), Sevmash General Director Mikhail Budnichenko told ITAR-TASS on 7 February.

Speaking at Defexpo 2014 in New Delhi, Budnichenko indicated that Sevmash will begin construction on two Borey SSBNs and one Yasen SSN in 2014.

The Borey SSBNs will be modernized Proyekt 955A submarines, reportedly stealthier than the first three Proyekt 955 boats. The Yasen SSNs will be improved Proyekt 885M submarines.

If Russia keeps to the schedule outlined by the Sevmash chief, it will put all remaining units of eight planned Borey SSBNs as well as seven Yasen SSNs into build.

The total number of Yasen-class submarines has been reported at six or seven at various times. They would include Severodvinsk (Proyekt 885) and either five or six Proyekt 885M boats.

Submarine Update

С новым годом ! !  Happy New Year ! !

To finish 2013, here’s some submarine news for anyone who might be a bit behind.

Oscar II SSGN Smolensk (K-410)

Oscar II SSGN Smolensk (K-410)

Yesterday Mil.ru and Interfaks reported Oscar II-class SSGN Smolensk has returned to Zaozersk, its Northern Fleet base, following two years of overhaul and modernization at Zvezdochka shipyard in Severodvinsk.

Its commander said the 24-year-old submarine successfully completed “tasks of the first phase of factory underway trials” as well as the transfer back to home base.

He said, in 2014, Smolensk will operate in “distant ocean areas” and surface at the North Pole to plant a Russian national flag and Navy ensign.

During the overhaul, the “technical readiness” of all systems, including hull and power plant, was reestablished.  Radioelectronic and navigation systems were modernized, according to Mil.ru.

An overhaul of Voronezh was completed in 2011, and Orel just arrived for refit.

The Oscar II overhauls indicate Russia is investing to keep its third generation nuclear sub numbers up, as Dmitriy Rogozin said it would in early 2012.

Shifting gears to proyekt 885 SSN Severodvinsk, RIA Novosti reported an industry source claimed this first unit of new attack submarines would be accepted at Sevmash on 30 December.

Didn’t happen.  But could soon.

Unit two, proyekt 955 Borey-class SSBN Aleksandr Nevskiy, however, officially joined the fleet on 23 December, according to RIA Novosti.

Aleksandr Nevskiy (photo: Sevmash)

Aleksandr Nevskiy (photo: Sevmash)

Mil.ru covered the acceptance ceremony.  Navy CINC Admiral Viktor Chirkov reconfirmed that Nevskiy will eventually report to the Pacific Fleet’s 25th DiPL at Vilyuchinsk.

But Russianforces.org yesterday covered the arrival of Nevskiy and unit one Yuriy Dolgorukiy at the Northern Fleet’s Gadzhiyevo base.  There, of course, they await the resolution of issues with their primary armament, the Bulava SLBM.

Nevskiy will test fire a Bulava again in 2014.

Unit three, Vladimir Monomakh, is supposed to enter the force in 2014.

Apparently, there was something to the General Staff source who told RIA Novosti that Nevskiy (and Monomakh) would be accepted without their complement of Bulava missiles.

Special Steel

Yasen Rollout in June 2010

On Thursday, Argumenty nedeli published a short article citing a source claiming Russia’s specialty steel makers aren’t very interested in supplying metal for new submarines planned for the Navy.

Argumenty’s record is interesting.  Sometimes they go out on a limb and don’t quite get a story right; other times they nail it or catch the gist of what seems to be happening.  Can’t say which it is this time.  But the paper has a tradition of looking closely at different parts of defense industry.

The story maintains Sevmash is trying to scrape together the specialty steel needed for new boats, and is short of what it needs for Borey– and Yasen-class hulls.  The paper’s OPK source notes, of course, that those boats already launched were assembled from existing sections of older submarine classes.

The source concludes rather direly:

“If the issue of steel isn’t resolved, then you have to forget about further production of our missile-carrying submarines.”

He continues:

“. . . it’s unprofitable for suppliers to produce.  Their own cost is high, but the Defense Ministry is buying a miserly quantity and trying to drive down the price on the finished item and, accordingly, on the components.”

Argumenty ends its short piece by reminding readers about the conflict between the Defense Ministry and United Shipbuilding Corporation (OSK) on the one hand and Sevmash on the other over pricing and contracts which lasted most of 2011.

That year-long battle ended in mid-November when Prime Minister Putin supervised the signing of seven submarine contracts worth more than 280 billion rubles in Severodvinsk.  There aren’t precise details on what the deal covered except nuclear-powered submarines — the modernized proyekt 955 Borey and proyekt 885 Yasen (or 955A and Yasen-M).

If Argumenty’s story is accurate, it suggests future disputes over submarine production and profit margins for Sevmash’s sub-contractors and suppliers.  Perhaps Putin’s deal was only a temporary end to the government-industry conflict.

Bulava Success

Interfaks and ITAR-TASS report Borey-class SSBN Yuriy Dolgorukiy successfully launched its third Bulava SLBM today, that’s the 17th overall test and the 10th success (including five in a row).

The earlier-reported launch window was missed due to bad weather, according to Flotprom.ru.

ITAR-TASS quoted the VPK this week regarding Borey unit 2 Aleksandr Nevskiy.  The VPK says Nevskiy won’t fire a Bulava before the summer of 2012.  After finishing its factory underway testing (ZKhI or ЗХИ) and several successful single Bulava launches, Nevskiy might be accepted into service by the end of 2012, according to the VPK.

Nevskiy’s now on a two-week phase of ZKhI and will be back in Severodvinsk by early December to rectify any problems identified.  ITAR-TASS says underway testing will continue as the weather permits.

Rossiyskaya gazeta Wednesday also noted that Nevskiy’s schedule has moved to the right, and it can’t be accepted until 2012.  RG covered how the first two Boreys used unused proyekt 971 Akula components, but some are talking about Borey unit three Vladimir Monomakh as a “modernized variant” and its builders will no longer be forced to stuff their “new contents” into a “different” hull.  Others have cited the lack of leftover parts as a problem that will increase the cost and difficulty of building the third new SSBN.

The paper says Nevskiy’s crew trained at Obninsk, and also aboard Dolgorukiy.  Like Dolgorukiy, Nevskiy will head for the Pacific Fleet, according to RG.  OSK and the Defense Ministry remain in difficult negotiations over the Borey’s reported 23-billion-ruble price tag.

Updating a related story, ITAR-TASS says new Yasen-class SSN Severodvinsk is now in its second underway period.  Its first (September until early October) was deemed successful; 80 percent of tasks were completed and only minor problems identified.

Worth recalling here that two Boreys, Bulava, and one Yasen were all on President Medvedev’s list of weapons systems to be procured in GOZ-2010.

Difficult Course to a Grand Fleet

Konstantin Bogdanov sees reason for pessimism when looking at the course ahead for rebuilding Russia’s fleet.  Writing in Friday’s Nezavisimoye voyennoye obozreniye, he says, despite an intention to spend 4.7 trillion rubles of the ten-year GPV on the Navy, there are technical challenges, clearly impractical schemes, and failures in what he calls the “organization-financial plan” ahead. 

Bogdanov provides us a handy review of the state of Russian shipbuilding.

He points first to OSK’s insistence on seeing new aircraft carriers (with nuclear-powered destroyers in their battle groups) on the Russian Navy’s horizon.  But Defense Minister Serdyukov has only a cold rebuff for the idea.  Early R&D into what a new carrier might look like is as far as he’s being willing to go.  It was made pretty clear that a carrier isn’t part of this GPV.

Bogdanov says OSK may be looking for work for the New-Admiralty Wharves it sees on Kotlin Island in the future.  The 30- to 60-billion-ruble shipyard could be ready in 2016.  An aircraft carrier project would help launch this idea.

Then Bogdanov turns to the Navy’s more immediate needs — frigates and corvettes.  

Proyekt 22350 frigates are needed by tens, if not 30, or even 40, of them.  But Northern Wharf is having trouble building them.  Lead unit Admiral of the Fleet of the Soviet Union Gorshkov was five years in construction, and its underway testing isn’t complete.  Fleet Admiral Kasatonov was laid down just about two years ago.  Its SAM system, Poliment-Redut with 9M96 missiles isn’t ready, and will have to be fitted right to finished frigates.  But Bogdanov sees the frigates’ VLS — the Multipurpose Ship Fire System (UKSK or УКСК) as a positive step.  It could fire antiship, antisubmarine, land-attack cruise missiles, torpedoes, and possibly SAMs.

When proyekt 22350 didn’t come along quickly, Bogdanov says, the Navy went for its own proyekt 11356M frigates like those being built for India.  But, he notes, Baltic Shipbuilding Plant “Yantar” in Kaliningrad isn’t having an easy time constructing them for its Indian and Russian customers.  There are delays in the Indian units, but Admiral Grigorovich and Admiral Essen have been laid down for Russia, and Admiral Makarov should join them soon.  The contract for a second batch of three was just signed.  They’re supposed to be “localized,” but may actually be more like the Indian versions.  They’re slightly cheaper than the proyekt 22350 at 10 billion vs. 16 billion rubles per ship.

Northern Wharf has the order for nine proyekt 20380 Steregushchiy-class corvettes (with the proyekt 22350 frigates this comes to more than 220 billion rubles).  Soobrazitelnyy (proyekt 20381) began sea trials this year, Boykiy was launched, Stoykiy is under construction, and Provornyy (proyekt 20385) was laid down.  Sovershennyy (proyekt 20380) remains under construction at Komsomolsk-na-Amure.  Bogdanov says the proyekt 20385 ships will have an eight-cell UKSK.

Bogdanov notes, however, that Northern Wharf’s production won’t be steady until its ownership issue is finally resolved.  If OSK takes over, this could have a good or bad effect on fulfilling defense orders, but the current financial questions around Northern Wharf are even worse.

Turning to submarines, Bogdanov believes the situation is more transparent, but there are still questions.

The SSBN picture is pretty clear.  Proyekt 955 Borey-class SSBNs finally have a missile that looks like it works.  Yuriy Dolgorukiy has fired it, and Aleksandr Nevskiy might this year.  Vladimir Monomakh is under construction, and they’re preparing production materials for Saint Nikolay.

The problem, he notes, is units 1 and 2 used sections and components of proyekt 971 and 949A submarines never built.  Units 3 and 4 will be built from scratch, and it’s too early to say how this will be reflected in their cost.  Bogdanov concludes another battle over inflated prices awaits, and there is, of course, still no 2011 contract with Sevmash.

It’s less clear with the multipurpose proyekt 885, Yasen-class, of which the Navy wants ten by 2020.  But these boats have been the focus of the Defense Ministry’s familiar complaint about unjustified price increases.  Unit 1 Severodvinsk was built from materials and resources on hand, and its rising price was frozen at 47 billion rubles in 2005.  The Defense Ministry says Sevmash wants 112 billion for unit 2 Kazan

Bogdanov thinks it’s hard to tell who’s justified here.  There is structural industrial inflation, and a higher costs could be the result of the frozen handover price on Severodvinsk.

Bogdanov mentions the thought given to cheaper attack boats like the Victor III or Akula, or proyekt 957 Kedr which never left the design phase.  The Yasen is intended to replace Soviet-era SSNs and SSGNs, but Bogdanov thinks it’s too complex and expensive to be built in the numbers Russia may need.  Twenty years ago the Russian Navy was planning for not less than 30 [sized of course against the U.S. fleet], and currently it has not more than 30 SSNs and SSGNs, and this is considered insufficient. 

Despite the uncertainty above, Bogdanov says one still hears talk about the need to develop a fifth generation submarine, but it’s unknown if there will be any development work on one.
 

Navy Day

Sankt-Peterburg Submarine in the Bolshaya Neva (photo: http://www.flot.com)

In honor of Navy Day — the 315th anniversary of the Russian Navy’s establishment — here are this week’s sound bites from Navy CINC, Admiral Vladimir Vysotskiy.  RIA Novosti will publish a complete interview with him tomorrow.

Vysotskiy says the Navy expects “not less than eight” proyekt 885 SSNs by 2020.  Some sources maintain the number is six.

Unit 1 Severodvinsk is preparing for sea trials in August, and unit 2 Kazan is expected by 2015.  They’ll have to pick up the pace to get eight by 2020.

Vysotskiy says work on a new destroyer will begin in 2012, and be completed in 2016.  This is the one he suggested might be nuclear-powered.

The CINC’s other comments covered the Black Sea Fleet. 

He claimed the BSF will get six proyekt 636 diesel-electric submarines in the coming years.  Its sole submarine now, proyekt 877 Varshavyanka-class SS Alrosa is currently in the Baltic for repair.

RIA Novosti recalled Vysotskiy’s past comments about obtaining 15 frigates and diesel submarines for the BSF by 2020 in a 60-30 proportion.  He also said a frigate and submarine were specifically laid down for the BSF in 2010, and would be every year henceforth.  He claimed the fleet would be renewed by 2020 through new construction rather than inter-fleet transfers.

Moskovskiy komsomolets and Newsru.com reported on the BSF’s drastic ten-fold decline since 1997.

This week TsAMTO cited a Baltic Fleet press release saying it expects to get the Neustrashimyy-class FF Yaroslav Mudryy, proyekt 20380 Steregushchiy-class FFLs Steregushchiy, Soobrazitelnyy, and Boykiy, proyekt 677 Lada-class SS Sankt-Peterburg, as well as assault ships and other craft.  The BSF may be expecting to get some of these ships as well.

Severodvinsk Trials and GOZ Tribulations

Severodvinsk (photo: RIA Novosti / Vladimir Rodionov)

Your typical good news, bad news story . . . happily for the Russian Navy, the Severodvinsk is nearing its first at-sea testing, but the new submarine has also been held up as a prime example of outrageous price increases in this year’s state defense order.  Final delivery of this SSN, as well as the first two Borey-class SSBNs, represents a big part of troubled GOZ-2011.

RIA Novosti reports new fourth generation Yasen-class (proyekt 885) SSN Severodvinsk will soon head into the White Sea for two months of underway testing, according to Malakhit Design Bureau General Director Vladimir Pyalov.  He added that, after this at-sea period, the final phase of state testing will take place.  

A very precise Mr. Pyalov says Severodvinsk is currently 98.9 percent complete.  He thinks the Navy will accept the new boat before year’s end and, in all, six of these multipurpose submarines will be built.  The second proyekt 885 Kazan is slated for delivery in 2015. 

RIA Novosti says proyekt 885 is a double-hulled, single-shaft boat with a reduced acoustic signature.  The conning tower has a streamlined, oval shape.  The boat is divided into ten compartments. 

For the first time, according to RIA Novosti, Russian designers put the submarine’s torpedo tubes amidships to allow for a new bow-mounted sonar system.  Proyekt 885 has eight vertical launch tubes for supersonic cruise missiles.  It has new communications and navigation systems as well as a fundamentally new nuclear power plant, according to the news agency’s report.  The new submarine is said to be first in noise reduction and stealth among attack submarines worldwide.

But the Severodvinsk couldn’t evade detection in the furor over breakdowns in the state defense order.

Earlier this month, RIA Novosti reported on disputes between the United Shipbuilding Corporation (OSK), submarine-builder Sevmash, and the Defense Ministry over naval construction in this year’s GOZ.  In particular, the military accuses the builder of doubling its prices for proyekt 955 Yuriy Dolgorukiy and proyekt 885 Severodvinsk.

An OSK spokesman defended Sevmash saying the cost of its work on Severodvinsk is only 30 percent of the total price, with the balance being the cost of armaments and components supplied by several dozen enterprises.  He blamed inflation in the industrial sector and the economy more generally.

Summarizing his discussion of submarines with OSK, RIA Novosti reports, Defense Minister Serdyukov said:

“They are giving us an increase in prices on new orders, and, naturally, we don’t agree with this.”

But, he added he’s convinced the Defense Ministry will persuade the producer to lower its prices.

Izvestiya mentioned that Severodvinsk was originally intended for a production run of 30 submarines, now reduced to six more than 20 years later.  As recently as March, the Navy still publicly hoped for ten.

Serdyukov told the paper:

“. . . it’s incomprehensible what the price of the ship [sic] consists of, if the cost of the lead boat was 47 billion rubles ($1.7 billion), but the next, exactly the same is now 112 billion ($4 billion).”

“Of course, the price will grow if, in the cost of one ship [sic], they include all accompanying expenditures on other enterprise projects in no way connected with it, like maintaining kindergartens, infrastructure, etc.”

“We’re prepared to pay, but on the condition that the price formation process will be transparent.  As practice shows, if all articles in the contracts are “decoded,” then it seems it’s possible with confidence to deduct up to 30% from the final cost of a finished product.”

These must be bitter words for an enterprise that went many, many years without completing its trademark product — a nuclear-powered submarine.

A Sevmash source says the cost of submarine construction is directly related to higher prices for materials, energy, and integration:

“The entire range of equipment for a submarine is supplied by monopolistic companies trying to dictate their prices.”

Nikolskiy on GOZ-2010 Failures

On Tuesday, Vedomosti’s Aleksey Nikolskiy wrote about breakdowns in last year’s State Defense Order (GOZ).  He notes that concern about failures started with Roskosmos, but it isn’t limited to that part of the defense sector.

Nikolskiy recounts Deputy Prime Minister Sergey Ivanov’s session with the Roskosmos collegium.  The space industry only produced five of 11 satellites specified in GOZ-2010, and 6 civilian launches were postponed.  The three GLONASS satellites lost to a “childish mistake” [in filling the rocket’s tanks] cost 2.5 billion rubles.  But we’ll return to Russia’s space woes another day. 

A Defense Ministry source tells Nikolskiy GOZ failures are constant. 

Bulava SLBM delays kept Yuriy Dolgorukiy from entering service [remember the new SSBN itself had to return to Sevmash for work while it awaits the next Bulava test].  Introduction of the new Severodvinsk SSN has been put off until much later because of construction defects.  A United Shipbuilding Corporation (OSK) source tells Nikolskiy the Defense Ministry has stopped financing completion of a proyekt 677 diesel-electric sub, and work on two others laid down at Admiralty Wharves is in question.

Nikolskiy says the Air Forces’ assimilation of Yak-130 trainers is delayed by last March’s crash.  And there’s a serious delay in the testing of the Su-35 fighter, according to a Defense Ministry officer [Sukhoy was reportedly testing two Su-35s last August].  One enterprise manager claims reforms in the Defense Ministry purchasing system are holding back contracting for aircraft deliveries this year. 

CAST’s Konstantin Makiyenko says government and Defense Ministry criticism of industry for its GOZ failures could be followed by personnel changes.  In Roskosmos’ case, the situation is almost “overripe.”  But Makiyenko defends other Russian arms producers by noting that delivery delays are common even for U.S. and European manufacturers.

Dolgorukiy, Bulava, Severodvinsk

Submarine-related news notes . . .

Russian press services have announced that the state commission on the Bulava has finished analyzing the results of the last two launches.  The next test will be in the second half of December, and the exact date will depend on White Sea weather conditions.

It’s pretty, but not absolutely, certain that new Borey-class SSBN Yuriy Dolgorukiy will be the launch platform.  The final decision on this will be made in the first ten days of December.  One supposes another shot from Dmitriy Donskoy remains a remote possibility.

If the pending launch is a success, the next phase of testing will begin in May 2011.

Regarding fourth generation (proyekt 885, Yasen) SSN Severodvinsk, the boat is still fitting out, and the Navy expects it to join the fleet in 2011.  Like DolgorukiySeverodvinsk was under construction for many years.  ITAR-TASS said this morning 6 of these submarines are now planned.